New factory capped and production line expanded

New factory capped and production line expanded

09 Oct, 2022

On September 10, 2022, after a year of construction, our new production base was successfully capped. The new production base is planned to cover an area of 7,000 square meters and a building area of 21,000 square meters. It is mainly used for the production of photovoltaic solar modules and supporting products. , According to project expectations, the equipment commissioning stage will begin in early November. The new production base will adopt fully automated production, with a planned annual output of photovoltaic modules of 500MW and an annual output of 150,000 sets of applied products. After the new production line is put into operation, the pressure of order delivery will be greatly relieved, the product qualification rate will be more assured, and customer needs will be further satisfied.